| Province | Subbasin | % |
|---|---|---|
| Columbia Plateau | Yakima | 100.00% |
| Previous: | Next: |
|---|---|
| 74314 REL 76: 1992-009-00 EXP YAKIMA PH II O&M |
* Expenditures data includes accruals and are based on data through 31-Oct-2025.
| Deliverable Title | WSE Sort Letter, Number, Title | Start | End | Concluded |
|---|---|---|---|---|
| Documentation and Assistance to Support BPA's Environmental Compliance Group | A: 165. Obtain EC Coverage for O&M Activities | 06/30/2020 | 06/30/2020 | |
| Construct 6 Drum Screens | B: 186. Construct 6 Drum Screens | 09/30/2021 | 09/27/2021 | |
| Install 2 Drum Screens | C: 69. Install 2 Drum Screens | 03/31/2021 | 03/31/2021 | |
| Refurbish 16 Gantries and Equipment Purchased/Received | D: 186. Refurbish 16 Gantries | 03/31/2021 | 11/13/2020 | |
| Fish screen site summaries | E: 174. Update Screen Records | 09/30/2021 | 09/30/2021 | |
| Survey Evaluations and Conceptual Designs | F: 175. Survey Evaluation/Produce Conceptual Designs - Snipes & Allen Bypass | 09/30/2021 | 09/30/2021 | |
| Survey Evaluations and Conceptual Designs | G: 175. Survey Evaluation/Produce Conceptual Designs - Buttermilk Head Structure | 09/30/2021 | 09/30/2021 | |
| Survey Evaluations and Conceptual Designs | H: 175. Survey Evaluation/Produce Conceptual Designs - Skyline Bypass | 09/30/2021 | 09/30/2021 | |
| Survey Evaluations and Conceptual Designs | I: 175. Survey Evaluation/Produce Conceptual Designs - Chewuck Control Spillway | 09/30/2021 | 09/30/2021 | |
| Install compliant profile bar screen panels | J: 69. Screen Replacement | 03/31/2021 | 03/31/2021 | |
| Effective implementation management and timely contract administration | M: 119. Manage and Administer Project | 09/30/2021 | 09/30/2021 |
| Primary Focal Species | Work Statement Elements |
|---|---|
| Chinook (Oncorhynchus tshawytscha) - All Populations |
|
| Coho (O. kisutch) - Unspecified Population |
|
| Steelhead (Oncorhynchus mykiss) - All Populations |
|
| Sort | WE ID | WE Title | NEPA | NOAA | USFWS | NHPA | Has Provisions | Inadvertent Discovery | Completed |
|---|---|---|---|---|---|---|---|---|---|
| A | 165 | Obtain EC Coverage for O&M Activities | |||||||
| B | 186 | Construct 6 Drum Screens | 03/31/2020 | ||||||
| C | 69 | Install 2 Drum Screens | 03/31/2020 | ||||||
| D | 186 | Refurbish 16 Gantries | |||||||
| E | 174 | Update Screen Records | |||||||
| F | 175 | Survey Evaluation/Produce Conceptual Designs - Snipes & Allen Bypass | |||||||
| G | 175 | Survey Evaluation/Produce Conceptual Designs - Buttermilk Head Structure | |||||||
| H | 175 | Survey Evaluation/Produce Conceptual Designs - Skyline Bypass | |||||||
| I | 175 | Survey Evaluation/Produce Conceptual Designs - Chewuck Control Spillway | |||||||
| J | 69 | Screen Replacement | |||||||
| K | 185 | Periodic Status Reports for BPA | |||||||
| L | 132 | No Annual Report | |||||||
| M | 119 | Manage and Administer Project |